Direct Transfer Trip (DTT) leveraging redundant cellular communication channels

Ieee account.

  • Change Username/Password
  • Update Address

Purchase Details

  • Payment Options
  • Order History
  • View Purchased Documents

Profile Information

  • Communications Preferences
  • Profession and Education
  • Technical Interests
  • US & Canada: +1 800 678 4333
  • Worldwide: +1 732 981 0060
  • Contact & Support
  • About IEEE Xplore
  • Accessibility
  • Terms of Use
  • Nondiscrimination Policy
  • Privacy & Opting Out of Cookies

A not-for-profit organization, IEEE is the world's largest technical professional organization dedicated to advancing technology for the benefit of humanity. © Copyright 2024 IEEE - All rights reserved. Use of this web site signifies your agreement to the terms and conditions.

PEguru logo

Substation Design | Power System Analysis

  • Permissive Overreaching Transfer Trip Scheme (POTT)

POTT scheme works using the following logic:

High-Speed Tripping Logic for POTT = Fault in Zone 2 AND permission-to-trip signal from remote end relay

POTT Trip Scenario No. 1:  Fault in the zone of protection

Permissive Overreaching Transfer Trip (POTT) Scheme: Scenario 1 - Fault in zone.

  • A fault on the t-line is picked-up by the zone 2 element of each relay.
  • Both relays key permissive signal to each other.
  • The relays go ahead and trip their respective breaker A & B.

POTT Trip Scenario No. 2:  Fault outside the zone of protection

Permissive Overreaching Transfer Trip (POTT) Scheme: Scenario 2 - Fault outside the zone of protection.

  • The fault is not covered by the relay at breaker B.
  • A permissive signal is NOT keyed to breaker A.
  • On the flip-side, breaker A relay does pick-up on this fault and transmits the permissive trip signal to the relay at breaker B.
  • Based on logic mentioned at the beginning of the article, line relays at breaker A and breaker B will not initiate a trip.
  • For this fault location, ideally, the bus differential relay would pickup and trip breakers B and C.

As mentioned above, POTT scheme relies on receiving a “permission to trip” signal from the remote-end relay and the local relay to initiate a breaker trip. The signal is keyed using a Frequency-Shift Keying (FSK) transmitter/receiver (see Ametek TCF-10B ).

Under normal conditions, the relay transmits a “guard” frequency. This frequency prevents the relay from operating.

Under abnormal conditions, the relay switches to a higher or a lower frequency to transmit a “trip” signal. When relays on both ends of the line shift to the “trip” frequency, only then are the breakers tripped.  The guard/trip frequencies are maintained and specified by the utility such that no two lines in the system use the same frequency.

POTT scheme and Power Line Carrier

Usually, POTT schemes do not get implemented over the power line carrier. A fault on the line may short-out the permissive trip signal, and with the lack of this signal, the relay operation gets inhibited. For this reason, facilities like leased telephone lines, fiber optics, or microwave radio are employed.

If you insist on implementing POTT using PLC then multi-phase coupling of the carrier signal is necessary (i.e. wavetrap, CCVT, tuner, et.al. installed on the 2nd or all 3 phases.) This provides redundancy for the secure operation of this scheme. Another alternative is to use the unblock scheme . The logic is quite similar to POTT with one minor variation.

This article, part of a series, covers the essentials on pilot relaying and pilot protection schemes. If not done already, start at the beginning.

  • Basics of Pilot Relaying & Application Considerations For Transmission Line Protection
  • Directional Comparison Blocking Scheme (DCB)
  • Directional Comparison Un-Blocking Scheme (DCUB)
  • Direct Transfer Trip Scheme (DTT)  (This is technically not a pilot scheme but requires a pilot channel)

4 thoughts on “Permissive Overreaching Transfer Trip Scheme (POTT)”

Pingback: Direct Transfer Trip Scheme | PEguru

Post updated based on user feedback

Can you please elaborate?

The explanation only covers the detail of communication signal. A good answer; anyhow, nothing is mentioned about the protection scheme itself. for example, which zone generates the signal and how it is compared on the other side relay

Leave a Comment Cancel Reply

Your email address will not be published. Required fields are marked *

Aleen Mohammed

Connect with me

direct underreach transfer trip scheme

  • Online Training
  • Access Your Courses
  • Group Registration
  • The Complete Relay Testing Handbook Series
  • Book Extras
  • Your Digital Downloads
  • Hands-On Training Class Information
  • Download Our Relay Training Brochure
  • TechTalk (Our Blog)
  • Add Your Post to TechTalk
  • We Need Your Help!
  • Why Choose Valence?
  • About Chris Werstiuk
  • Testimonials
  • Contact Valence
  • Subscribe to our Mailing List
  • Your Shopping Cart
  • The Relay Testing Handbook
  • Your Account Info

No products in the cart.

Understanding Permissive Over-Reaching Transfer Trip (POTT) Communication Assisted Trip Schemes Video

Here is the latest video describing the Permissive Under-Reaching Transfer Trip Communication-Assisted Trip Schemes used in modern distance protection.

You can follow along with this animation via the Can You Predict What Happens in a Permissive Over-Reaching Transfer Trip (POTT) Scheme? post found under the Testing handbooks / Book Extras menu.

You can also get more information about End-to-End Testing and all of the communication-assisted trip schemes via The Relay Testing Handbook: End-to-End Testing .

Here’s the video:

Here’s a transcript:

Welcome to the fifth video in our end-to-end testing series.  We’ll be looking at a Permissive Over-reaching Transfer Trip, or POTT, communication-assisted trip scheme in this video.

I’m going to assume that you’ve watched the previous videos in this series; so I won’t rehash what to look for in this animation. If you have not watched the previous videos, stop now and click this link to watch them first, so you can follow along.

Now that the introductions are out of the way, we can start by decoding the term POTT:

  • The “P” stands for “Permissive.” A Permissive scheme tells the other relays protecting a line that they can trip faster if they ALSO detect a fault in the correct direction. All relays must agree that there is a fault on the line before a Permissive trip is allowed, unlike the direct scheme that would send a trip signal if only one relay detected a fault. Permissive schemes share information back and forth, so you will need your fancy GPS and/or IRIG connected equipment on ALL sides of the line.
  • The “O” stands for “Over-reaching”. Zone-2’s pickup impedance is typically set larger than the protected line, which means at least one relay must measure a Zone-2 fault for this scheme to work.
  • “TT” means that at least one relay is sending a Transfer Trip signal to the other relays in the scheme.

You’re looking at an animation of a traditional POTT scheme that you can find on our website, relaytraining.com.  There should be a link on the screen right now that you can open in a new window if you want to follow along. The link can also be found in the description below.

Which elements will pick up in Relay-1 if a fault occurs close to Relay-1 as we show here?

Which elements will pick up in Relay-2?

Zone-1 AND Zone-2 will pick up in Relay-1 because the fault is closest to Relay-1, while only Zone-2 will pick up in Relay-2.

Relay-1 will trip instantaneously because of the Zone-1 pickup, but it will also send a POTT signal to the other relay because it has detected a Zone-2, or potential over-reaching, fault on the line.  We call Zone-2 an Over-reaching condition because it is purposely set somewhere around 120% of the line as we described in the previous videos. Zone-2 is purposely set to detect faults in the section between the Zone-1 limit and the rest of the line, AND it provides backup protection for faults on other lines in the forward direction. This means that Zone-2 will detect faults that may not be on the transmission line this relay is installed to protect.

The fault is still on the line even though Relay-1 tripped and current is flowing through Relay-2. How long will it take before Relay-2 trips?

Relay-2 would normally trip after a 20-40 cycle Zone-2 time delay in a standard impedance protection scheme, but Relay-2 received a Permissive Over-Reaching Transfer Trip from Relay-1. This POTT signal from the other relay gives Relay-2 PERMISSION to trip faster IF it also detects a Zone-2 pickup. The permissive signal AND Zone-2 pickup means that Relay-2 will trip after a short communication time delay, which is usually less than 3 cycles.

Let’s look at a fault that is closer to Relay-2, but this time we’ll compare it to a standard distance protection scheme.

This fault is a mirror image of the previous one with the standard distance scheme on the top of the screen, and the POTT scheme shown on the bottom of the screen. Which elements will pick up in Relay-1 and 2?

This time Relay-2 sees a Zone-1 and Zone-2 pickup, while Relay-1 sees a Zone-2 pickup.

Relay-2 will trip instantaneously in both protection schemes because Zone-1 will always trip first because it has no intentional time delay.

Relay-1 should trip in 20-40 cycles in the normal protection scheme at the top of the screen because it has detected a Zone-2 fault, which means that the fault could be on the line the relay is supposed to protect, OR it could be on the line Relay-4 is installed to protect. Therefore, it is going to wait for Relay-4 to trip in case the fault is on Relay-4’s line. If Relay-4 doesn’t operate, Relay-2 will trip after a time delay.

The POTT scheme on the bottom of the screen will NOT wait for Relay-4 to operate because it is getting feedback from Relay-2 that indicates that the fault is on the line. If Relay-1 and Relay-2 both detect a Zone-2 fault, that means the fault should be in the overlapping region between the two relays, which is 100% of the line. Relay-2 will trip after a short communication time delay and remove the fault from the system.

A POTT scheme has pretty simple operating characteristics. If all the relays protecting a line detect a Zone-2 pickup, then the fault must be on the line; therefore, there is no reason to wait for the normal 20-40 cycles.

However, I bet the POTT schemes installed at your sites are more complicated than what I’ve described here because POTT schemes have a glaring weakness that we can demonstrate in this animation:

This animation can also be found on our website and depicts POTT schemes installed on parallel lines. Current flows from right to left under normal conditions. Then a fault occurs on one line.

Relay-1 detects a Zone-1 and Zone-2 fault, while Relay-2 detects a Zone-2 fault. The standard POTT scheme logic applies. Relay-1 will trip with no intentional time delay, and Relay-2 should trip after a short communication delay. It looks like a standard fault for Relay-1 and Relay-2, but let’s look closer at Relays 5 and 6.

Relay-5 detects a Zone-3 fault because there is a parallel path for current to flow into the fault and the fault appears to be behind Relay-5. Reverse zones are typically used to detect reverse faults in communication-assisted trip schemes and don’t trip anything, or they have long time delays of 60-120 cycles. Relay’s 1 and 2 are going to isolate the fault long before Relay-5’s Zone-3 gets a chance to trip anything. So far so good.

Relay-6 could detect a Zone-2 fault, which has a 20-40 cycle time delay, so it probably won’t have a chance to trip either. BUT… it will send a Permissive trip signal to Relay-5.

Now let’s see how the relays respond to this fault.

Relay-1 trips instantaneously as we predicted, but there was a source connected to Relay-3, which is now the primary source for fault current.

Relay-2 still detects a Zone-2 fault and had received permission to trip for the POTT scheme, so it’s primed to trip after a short communication delay.

The current suddenly changed direction in Relay-5, so it no longer detects a Zone-3 fault and it could now detect a Zone-2 fault. Zone-2 has a long time delay, so that shouldn’t be a problem because Relay-2 should be tripping momentarily.  BUT… Relay-6 was sending a POTT permissive before Relay-1 tripped. Relay-5 detects a Zone-2… AND it could still be receiving a POTT signal from Relay-6 because communication signals will always be slower than locally processed information, such as the Zone-2 pickup. This means Relay-5 could be primed for a POTT operation.

We now have a race between Relay-2 and Relay-5.  If Relay-5 wins that race, we could lose both lines for a fault on the one line, which could be a major problem.

This weakness is inherent in any over-reaching communication-assisted trip scheme, and most schemes add additional logic to minimize this problem as shown in this revised drawing.

Zone-3 is looking in the reverse direction and is connected to a new drop-out timer, which is connected to a NOT symbol on the POTT Scheme. All of the relays detect the same zones when all breakers are closed in this new hybrid scheme, and now:

  • Relay-1 detects a Zone-1 Pickup and will trip instantaneously. Relay-1 also sends a POTT permissive trip signal to Relay-2 because it detects a Zone-2 pickup, and it did NOT detect a Zone-3 pickup in the last 5 cycles.
  • Relay-2 should trip on POTT after a short communication delay because Relay-2 detects a Zone-2 pickup, AND it’s receiving a POTT permissive signal from Relay-1, AND it has NOT detected a Zone-3 pickup in the last 5 cycles.
  • Relay-5 detects a Zone-3 reverse fault and sends a block signal to its POTT scheme.
  • Relay-6 detects a Zone-2 pickup and sends a POTT permissive signal to Relay-5.

All the relays operate normally so far.

Breaker-1 operates with no intentional time delay, which will cause a sudden current reversal through relays 5 and 6. Relay-5 now detects a Zone-2 fault, and it could detect a POTT permissive because Relay-6 may not have had time to release its previous permissive signal yet. This was a problem in the old scheme, but Relay-5 detected a Zone-3 reverse fault a moment before, so the Drop Out timer will hold the Zone-3 input to the POTT scheme on. The NOT logic gate reverses the input and the POTT scheme cannot operate for 5 cycles, which should give Relay-6 plenty of time to release its POTT permissive signal.

We no longer have a race between Relays 2 and 5.  Relay-2 will operate after a short time delay and the fault will be isolated from the system without affecting the non-faulted line. The scheme’s weakness has been beaten into submission with logic!

The dirty little secret of communication-assisted trip schemes is they all have the same operating characteristics under normal operating conditions. All end-to-end tests should be performed on either side of each protective zone to make sure the protected line is isolated faster when a communication-assisted trip scheme is applied.

However, POTT schemes require additional tests that prove that the Zone-3 timer is appropriate for the application by simulating a phase reversal from both directions.

Thanks for watching this video. I hope you have some new insights into how Permissive Over-reaching Transfer Trip communication-assisted trip schemes work.

You can play with this animation, and more, by following the link on the screen.  You can also get more information about testing these schemes in The Relay Testing Handbook: End-To-End Testing using the other link in this video, or reading the description below.

As always, please like this video and subscribe to our channel to let Google know we have good stuff.  It helps us get noticed and allows us to keep providing free content like this with no ads.

Don’t forget to have fun out there.

 Did you like this post?

You can share it with these links:

Author Image

About the Author

Chris Werstiuk  

Chris is an Electrical Engineering Technologist, a Journeyman Power System Electrician, and a Professional Engineer. He is also the Author of The Relay Testing Handbook series and founder of Valence Electrical Training Services. You can find out more about Chris here .

Read More Articles:

How to Perform an In-Service Protective Relay Meter Test

Use Sequence Components To Make Sure Your Relay Isn't Disabled By Incorrect Phase Rotation

Leave a Reply

Your email address will not be published. Required fields are marked *

You have really carved out a place for yourself in Electrical Power System protection. Good on you sir, well done.

The lecture is useful! We hope you have more useful lectures! Thanks

Very interesting and helpful. Thank you.

Where can I find the previous 4 videos mentioned? I would like to watch all the videos for this series. Great info.

Thanks for the kind words.

You can find them on our YouTube channel here https://www.youtube.com/watch?v=s_IrsNHv4aQ&amp

Very good explanation and well illustrated. Great job!

Wow, such an amazing explanation. Kudos all the way from Brazil.

IMAGES

  1. Direct Transfer Trip and Direct Under-Reaching Transfer Trip Schemes Video

    direct underreach transfer trip scheme

  2. Direct Transfer Trip Scheme

    direct underreach transfer trip scheme

  3. Direct Transfer Trip Scheme

    direct underreach transfer trip scheme

  4. Example of direct transfer trip scheme

    direct underreach transfer trip scheme

  5. Pilot schemes for transmission line protection

    direct underreach transfer trip scheme

  6. Understanding Permissive Over Reaching Transfer Trip POTT Communication Assisted Trip Schemes Video

    direct underreach transfer trip scheme

VIDEO

  1. PUTT Permissive Under Reach Transfer Trip Distance Protection Teleprotection Line Protection schemes

  2. Transfer day!// Transfer trip day 3// Surrogacy

  3. Fernbus Simulator: Denmark Transfer Trip from Kolding Station Mazantigade to Kopenhagen Airport

  4. How to transfer trip unbilled to billed section

  5. Explanation of Communication schemes in distance protection relay

  6. 11 Permissive Overreach Transfer Trip Scheme

COMMENTS

  1. Pilot schemes for transmission line protection

    Figure 3 - Direct Underreach Scheme. Go back to contents ↑. 1.4.2 Permissive Underreach. This scheme is identical to the direct underreach scheme with the addition of an overreaching fault detector. The transfer trip signal requires local confirmation by this fault detector before tripping can occur.

  2. PDF C4 Distance Protection Schemes

    a direct transfer trip or intertrip technique, the logic of which is shown in Figure C4.4. A contact operated by the Zone 1 relay element is arranged to send a signal to the remote relay requesting a trip. The scheme may be called a 'direct under-reach transfer tripping scheme', 'transfer trip under-reaching scheme', or 'intertripping

  3. Direct Transfer Trip and Direct Under-Reaching Transfer Trip Schemes

    The next scheme that we want to look at is the Direct Under-Reaching Transfer Trip and just like the Direct Transfer Trip scheme, Direct means that there's no communication happening between the two relays. One relay sends the command to the other relay. So once again, there's no reason for you to get out all your fancy GPS test equipment ...

  4. Direct Transfer Trip and Direct Under-Reaching Transfer Trip ...

    We're continuing our end-to-end testing series by looking at the two simplest communication-assisted trip schemes used. Watch this Direct Transfer Trip and ...

  5. PDF Practical Assessment of POTT and DCB Teleprotection Schemes Using

    proposed the use of the modified Direct Transfer Trip (DTT) teleprotection scheme for a closed circuit distribution network, using an OMICRON CMC-356 test box for its validation. Methodologies based on the use of computational platforms are also commonly reported for analysis and evaluation of teleprotection schemes.

  6. PDF Design and Implementation of IEC 61850 in Communication-Assisted

    differential, POTT, Permissive Underreach Transfer Trip, Direct Underreach Transfer Trip, Directional Comparison Unblocking Scheme, Directional Comparison Blocking Scheme, Direct Transfer Trip, and etc. By sharing the common and differentiating their own characteristics, there are also many different hybrid combinations of these schemes.

  7. Adaptive Direct Underreaching Transfer Trip Protection Scheme for the

    The direct underreaching transfer trip (DUTT) scheme used for the protection of the three-terminal transmission line operates when at least one of the three zone 1 elements detects an internal fault. This scheme uses a dedicated communication system to transfer the decision from one end to the other ends. The DUTT scheme is reliable until the overlappings between zone 1 settings are ensured ...

  8. Adaptive Direct Underreaching Transfer Trip Protection Scheme for Three

    Abstract. Direct underreaching transfer trip (DUTT) scheme used for protection of three-terminal transmission line operates when at least one of the three zone 1 elements detects an internal fault ...

  9. PDF Study of Coordination on Protection Relay in High Voltage ...

    For the DUTT pattern logic, the circuit scheme can be shown in Figure 5. Fig. 6. Logic circuits direct underreach transfer trip - Permissive Underreach Transfer Trip (PUTT) The working principle of the PUTT pattern is: if the disturbance felt at the one release distance zone, the relay will send a trip signal to CB.

  10. Direct Transfer Trip and Direct Under-Reaching Transfer Trip Schemes

    We're continuing our end-to-end testing series by looking at the two simplest communication-assisted trip schemes used. Watch this Direct Transfer Trip and Direct Under-Reaching Transfer Trip Schemes Video to learn more about these two schemes.

  11. PDF Statistical Comparison and Evaluation of Pilot Protection Schemes

    Figure 2: Years to a Time-Delayed Trip for POTT, DCUB, and DCB Protection Schemes The communication channel routing can have an impact on these figures. For instance, in a transfer-tripping scheme, there is a higher likelihood of a time-delayed trip due to failure to receive permission if the channel is in the line right-of-way.

  12. PDF ECE 526: Lab 2

    Lab 2, Page 2/2 Spring 2017. The settings start on page 5 of the relay model file. Set the following: Line impedance settings for both relay 1 and relay 2. Set the zone 1 and zone 2 reach settings. Task 1: Set DUTT scheme and POTT scheme with self-polarization. Test the relay with the provided COMTRADE files with non-zero fault resistance for ...

  13. Application Considerations for Protecting Three-Terminal Transmission Lines

    overreaching transfer trip schemes can have dependability issues; whereas, directional comparison blocking schemes face both ... from a line terminal can cause a distance relay underreach to [1] [2] [3]. The example system of 1 shows how current Fig. ... protection scheme and settings applied explained in the . This is following:

  14. Practical assessment of POTT and DCB teleprotection schemes using

    On the other hand, in [5] it was proposed the use of the modified Direct Transfer Trip (DTT) teleprotection scheme for a closed circuit distribution network, using an OMICRON CMC-356 test box for its validation. Methodologies based on the use of computational platforms are also commonly reported for analysis and evaluation of teleprotection ...

  15. Understanding Permissive Under-Reaching Transfer Trip (PUTT

    If the scheme starts with the letter D, the D can stand for "Direct" or "Directional." Relays do not share information back and forth in a "Direct" scheme. One relay simply tells the other relay to trip, and the other relay follows the command. The TT at the end of an acronym stands for "Transfer Trip."

  16. Direct Transfer Trip (DTT) leveraging redundant cellular communication

    This is achieved via Direct Transfer Trip (DTT) signals, traditionally sent between substations and remote DG sites using leased telephone lines. Due to the highly specialized and critical nature of DTT systems, the equipment, including the communication infrastructure, must be extremely reliable and conform to highest substation standards.

  17. Direct Transfer Trip Scheme

    Direct Transfer Trip Scheme (DTT) (This is technically not a pilot scheme but requires a pilot channel) Direct Transfer Trips (DTT) are initiated from station relays when a serious event occurs in the substation. Some of these events are breaker failure, bus faults, transformer failure, etc. A lockout relay (86 device) is assigned to each event.

  18. TRANSMISSION LINE PROTECTION USING POTT SCHEME A Project Presented to

    Permissive Overreaching Transfer Trip (POTT) is a scheme that enables fast tripping of breakers at the local and remote end of a protected equipment. POTT schemes are typically used for high voltage line protection against faults in areas with coordination and power stability issues. Three-phase fault is the most severe type of fault that can

  19. Breaker failure protection applications of modern numerical distance

    The inclusion of a direct transfer trip (DTT) bit and a reclose-blocking bit in the same digital message improves the breaker failure function and prevents reclosing into a faulted breaker. The pilot digital communications channel provides superior performance when compared to traditional communication channels regarding security, availability ...

  20. Can You Predict What Happens in a Permissive Under-Reaching Transfer

    The Relay Testing Handbook: End-to-End Testing covers the most common Communication-Assisted Protection Schemes including the Permissive Under-Reaching Transfer Trip (PUTT) Scheme. This bonus animation shows the steps involved for a PUTT trip. End-to-end testers should understand how this scheme operates before they test it and this animation was created to help relay testers understand ...

  21. Adaptive Direct Underreaching Transfer Trip Protection Scheme for the

    The direct underreaching transfer trip (DUTT) scheme used for the protection of the three-terminal transmission line operates when at least one of the three zone 1 elements detects an internal fault. This scheme uses a dedicated communication system to transfer the decision from one end to the other ends. The DUTT scheme is reliable until the overlappings between zone 1 settings are ensured.

  22. Permissive Overreaching Transfer Trip Scheme (POTT)

    As mentioned above, POTT scheme relies on receiving a "permission to trip" signal from the remote-end relay and the local relay to initiate a breaker trip. The signal is keyed using a Frequency-Shift Keying (FSK) transmitter/receiver (see Ametek TCF-10B ). Under normal conditions, the relay transmits a "guard" frequency.

  23. Understanding Permissive Over-Reaching Transfer Trip (POTT

    Relay-2 would normally trip after a 20-40 cycle Zone-2 time delay in a standard impedance protection scheme, but Relay-2 received a Permissive Over-Reaching Transfer Trip from Relay-1. This POTT signal from the other relay gives Relay-2 PERMISSION to trip faster IF it also detects a Zone-2 pickup.